← Proyectos

Cumplimiento & materiales

En progreso

NORTH MIAMI SENIOR HIGH SCHOOL

PM: CARLOS HERRERA ISM#: 1766702 13110 NE 8th Ave, North Miami, FL 33161
Crew: 2 techs 40 hrs/tech 80 man-hrs 5 días est.

This project consists of furnishing and installing a complete CAT6 structured cabling system, including horizontal cabling, telecommunications room upgrades, testing, certification, labeling, and project documentation. Total new drops: 75

Ítems SOW
1 / 9 ítems
Paso a paso del alcance
Drops / qty SOW
22.5%
27 / 120
Horas labor
0%
0 / 80 hrs
Materiales
0%
0 / 14 líneas completas

Media Center

Room 1310 — CAT6 data drops

Install twenty-seven (27) CAT6 data drops on (Media Center) Room 1310.

Hecho
/ 27 drops

2nd Floor

Room 2252 — CAT6 data drops

Install twenty-four (24) CAT6 data drops of Room 2252.

Pendiente
/ 24 drops

2nd Floor

Room 2253 — CAT6 data drops

Install twenty-four (24) CAT6 data drops of Room 2253.

Pendiente
/ 24 drops

Media Center IDF

Patch panel — Room 1305

Install one (1) new 48-port CAT6 patch panel in Media Center IDF Room 1305.

Pendiente
/ 1 ea

Telecom Room

Patch panel — Room 2258

Install one (1) new 48-port CAT6 patch panel in Telecom Room 2258.

Pendiente
/ 1 ea

Pathways

2" EMT sleeves

Install 2-inch EMT sleeves for pathway transitions.

Pendiente
/ 1 lot

Pathways

J-Hooks overhead support

Install support infrastructure (J-Hooks) along overhead crawl spaces.

Pendiente
/ 1 lot

IDF Pathway

2" EMT conduit into IDF rack

Install 40 feet of 2-inch EMT conduit pathway into the IDF up to the rack.

Pendiente
/ 40 FT

Infrastructure

Test, certify, label & document

Test, certify, label, and document all installed cabling.

Pendiente
/ 1 lot

Cable Pulling

Horas planificadas en el bid: 40 hrs

Pendiente
/ 40 hrs

Conduit & Pathway Installation

Horas planificadas en el bid: 12 hrs

Pendiente
/ 12 hrs

Terminations (Jacks & Panels)

Horas planificadas en el bid: 8 hrs

Pendiente
/ 8 hrs

Faceplate Installation

Horas planificadas en el bid: 4 hrs

Pendiente
/ 4 hrs

Labeling (Point-to-Point)

Horas planificadas en el bid: 4 hrs

Pendiente
/ 4 hrs

Testing and Certification

Horas planificadas en el bid: 8 hrs

Pendiente
/ 8 hrs

Patch Panel Installation

Horas planificadas en el bid: 4 hrs

Pendiente
/ 4 hrs

Copper Cabling

CAT6 Plenum Cable

Bid: 10500 FT · Restante: 10500 · 0%

FT

Patch Panels

48-Port CAT6 Patch Panel

Bid: 2 Qty · Restante: 2 · 0%

Qty

Keystones & Jacks

CAT6 Keystone Jack

Bid: 75 Qty · Restante: 75 · 0%

Qty

Faceplates

Dual Port Faceplate

Bid: 38 Qty · Restante: 38 · 0%

Qty

Patch Cords

CAT6 Patch Cord 3 FT

Bid: 75 Qty · Restante: 75 · 0%

Qty

CAT6 Patch Cord 7 FT

Bid: 75 Qty · Restante: 75 · 0%

Qty

Consumables & Hardware

Velcro Strap (Rolls)

Bid: 3 Qty · Restante: 3 · 0%

Qty

Pathways & Supports

J-Hook 2"

Bid: 50 Qty · Restante: 50 · 0%

Qty

2" EMT Conduit

Bid: 40 FT · Restante: 40 · 0%

FT

2" EMT Set-Screw Couplings

Bid: 4 Qty · Restante: 4 · 0%

Qty

2" EMT Set-Screw Connectors

Bid: 2 Qty · Restante: 2 · 0%

Qty

2" Plastic Bushings

Bid: 6 Qty · Restante: 6 · 0%

Qty

Unistrut Channel

Bid: 10 FT · Restante: 10 · 0%

FT

2" Strut Clamps

Bid: 8 Qty · Restante: 8 · 0%

Qty

Historial

Últimos movimientos

  • complete · sow
    Room 1310 — CAT6 data drops
  • seeded · project
    Proyecto NORTH MIAMI SENIOR HIGH SCHOOL cargado desde BID/SOW.